Two RFI deadlines, traced back to the field report.

ArchX consolidated RFIs and changes, identified the follow-ups at the review date and kept the evidence behind each reported status in an editable register.

Riverside Branch Library · RFI and change records · Recorded October 13, 2026 · Fictitious project, actual ArchX output

Inside the original output

Which answers were missing at the recorded review?
RecordReported due dateAt 13 October 2026
RFI 015 · roof drain sump depth22 September21 days past, if still open
RFI 016 · shelving blocking height1 October12 days past, if still open
CR 003 · Extra shelving blockingNo due date suppliedPending owner review

The latest status evidence is the September 29 field report. Later closure records were not supplied; the register does not establish that either RFI remains open today.

Original ArchX construction administration register showing the RFIs and change records from the Riverside review.
Actual CA workbook · Register tab, rows 1–7Enlarge ↗

What you can do with it

Chase the roof-drain and shelving responses, record any later closure evidence, and keep the pending change separate from signed changes.

The deliverable

Open what ArchX produced.

Original files from this run. No sign-up.

No prior register was supplied. This is a new consolidation of the available test documents, not an update to an unseen live register.

The starting point

What ArchX received.

Read the original request and file list

The request

Pay app #4 from Gulf Coast Builders for Riverside Library came in (Pay application/). Review it against the payment terms in our agreement excerpt (Contract/), the change order log and our field report from 9/29 (Site/). Recompute what's actually due, line by line, and tell me what I can recommend for certification and what I can't, and why. Then update our CA register with the RFIs and change items from the field report so we know what's overdue. Editable files, please.

The project files

  • Site observation notes 09-29.docx
  • Change order log.pdf

Try it on a job you know

Give it the task.
Then keep going.

Describe the work in your own words. Start with a project you know, inspect the result and ask for the next change in the same conversation.

Bring these files

A field report, change log and any existing RFI or change register.

What to check

Follow one RFI back to its source. Check its status, deadline and next action against what your team knows.

Before using client files, review how ArchX handles project data.

What could you ask next?

A suggested follow-up, once you have reviewed the result and added the new files:

I have added the latest RFI responses and change log. Update the register from those records and prepare a short follow-up list for the next meeting.

Download for Mac or Windows, connect your ChatGPT account or API key, then give ArchX this request with your files. AI usage runs through your connected account. Pricing and account requirements.