Pay application review.
How much can you certify?
A test pay application on a G703-style sheet, checked line by line: $466,220 requested, $363,224 certifiable, with retainage and stored materials.
How does an architect review a pay application?
Whether it comes on AIA G702 and G703 or a contractor’s own forms: check the arithmetic on every line of the schedule of values, compare the claimed progress with what you saw in the field, take in change orders only once executed, test stored materials against what the agreement requires, apply retainage at the agreement’s rate and basis, and deduct previous certificates as certified, not as paid. Then certify the supported amount or give written reasons for each adjustment to the owner and the contractor, within the time your agreement sets. In the test agreement that was seven days from receipt.
What moves the number
Our test application carried four planted errors of the kind that come up in practice. Check each of them:
- Stored materials off site without what the agreement asks for: bill of sale or invoice, insurance, the owner’s approval of the location.
- Retainage reduced at 50% complete when the agreement allows no reduction.
- Previous certificates taken as the cash paid, not the amount certified.
- A line total that does not add up to its own columns.
What stays out, and what stays in
Pending change requests stay outside the contract sum until executed. Supported items stay in: in the example, equipment stored on site, invoiced and insured was accepted, and a dispute over an earlier certificate stayed with that certificate rather than being certified or deducted again. Where the record gives no defensible figure, say what has to be resolved before signing.
How to do it.
- 01
Gather the record
The application and its backup, the agreement, your certificate log, the change order log and the field reports.
- 02
Check the arithmetic
Every schedule of values line and the summary.
- 03
Test eligibility
Stored materials, change orders and progress against the field report.
- 04
Apply the agreement
Retainage at its rate and basis; previous certificates as certified.
- 05
Worksheet and letter
A worksheet you can check, and a draft letter with each adjustment and its basis.
A test project: Pay Application No. 5 on a medical office building.
On a U.S. test project, ArchX reviewed the application against the agreement, the certificate log and the field report, then wrote the worksheet, a workbook with formulas and a draft letter to the contractor.


ArchX working time, measured
less than the contractor requested: $466,220.28 requested, $363,224.16 recommended for certification
planted errors found: off-site stored materials without evidence, retainage cut to 5% against the agreement, previous certificates taken as cash paid, and a line total off by $1,000
Test project: U.S., with planted errors. A fictitious firm, owner and contractor, a medical office building under a supplied owner-contractor agreement. One run with ChatGPT Pro (GPT 6.1 Sol, very high) and the same code as ArchX 0.1.3, sent to every firm on November 6, 2026. See the whole result
Asked briefly.
Does ArchX certify the payment or fill in AIA forms?
No. The review is a working draft, not a certificate for payment and not an AIA G702 or G703. You check it and certify; ArchX keeps the letter as a draft and sends nothing.
Does it read a G703-style continuation sheet?
Yes. The example application carries a continuation sheet with scheduled value, work from previous applications, this period, materials presently stored, total completed and stored, balance to finish and retainage, and the worksheet mirrors those columns.
Can I check the figures?
Yes. The worksheet shows the bridge from the requested to the reviewed amount, and the workbook holds the same figures as formulas.
What about items that are not an error?
They stay in. In the example the $41,200 of on-site equipment was supported and remained included, and ArchX named one open point, the roofing value split, to resolve before signing.
How long does it take?
In the example 5 min 34 s of ArchX working time, measured. You then check the result.
Sources, read November 7, 2026: AIA Contract Documents: how to complete the G702
Try it on your own work.
Download ArchX for Mac or Windows and give it a task from your firm. 7 days free with your ChatGPT account (Plus or higher).
