Construction administration.
Pay apps reviewed.
ArchX reviews the contractor’s pay application against the schedule of values, approved change orders and retainage.

What goes in.
You
Lone Mesa Builders submitted Pay Application No. 5 for the Bluebonnet Ridge MOB (Contractor/Pay Application No 5.pdf, with the stored materials backup). Please review it against the agreement, our certificate log and the field report and tell me how much I can certify. I need a review worksheet I can check and a draft letter to Lone Mesa explaining any adjustments.
Files
- Pay Application No 5.
pdf - Pay Application No 5 -
Stored Materials Backup. pdf - Owner-
Contractor Agreement - excerpt. pdf - Certificate Log.
xlsx - Change Order Log.
xlsx - Field Report FR-
14. pdf - COR-
07 Suite 140 Exam Rooms. pdf - PR-
05 Suite 140 Exam Rooms. pdf - Schedule Update 06.
pdf
Test project: U.S., with planted errors. A fictitious firm, owner and contractor, a medical office building under a supplied owner-contractor agreement. One run with ChatGPT Pro (GPT 6.1 Sol, very high) and the same code as ArchX 0.1.3, sent to every firm on November 6, 2026.
What ArchX gives back.



From the answer
I recommend certifying $363,224.16, a $102,996.12 reduction from the request. This carries the $79,650 roofing claim; confirm the membrane/coping value split before signing.
Agreement §4.3 requires 10% retainage through Substantial Completion. Section 4.4’s off-site storage requirements are unsupported; the insurance confirmation expressly excludes unscheduled off-site locations. The $41,200 HVAC storage claim is supported and remains included.
Previous certificates total $854,946, while cash paid totals $847,746. The disputed $7,200 BC-01 withholding stays with Certificate No. 4.
Before signing: resolve the roofing value split. Agreement §4.2’s November 3, 2026 deadline has passed; check for any earlier notice, then promptly issue certification or written adjustment reasons to both Owner and Contractor and request corrected application sheets. The draft letter remains unsent.
Saved files
- Payment Review Worksheet DRAFT.
pdf – Review worksheet: submitted against reviewed, the bridge to the amount, the reviewed continuation sheet, review notes and sources - Payment Arithmetic Review DRAFT.
xlsx – The same figures as formulas, to recalculate - Pay Application No 5 -
Adjustment Letter DRAFT. – Draft letter to the contractor with each adjustment and its basis; not sentdocx and . pdf
Measured, not estimated.
ArchX working time for this brief, measured.
Run of November 6, 2026
less than the contractor requested: $466,220.28 requested, $363,224.16 recommended for certification
Run of November 6, 2026
planted errors found: off-site stored materials without evidence, retainage cut to 5% against the agreement, previous certificates taken as cash paid, and a line total off by $1,000
Run of November 6, 2026
the amount matches our control calculation: $363,224.16, and the supported $41,200 on-site equipment stayed in
Run of November 6, 2026
How to.
Put the pay application, the schedule of values and the approved change orders in the project folder and ask for the review. Try ArchX free for 7 days with a task from your own firm.
