Costs.
From your drawings and unit costs.

ArchX prices the work from your drawings, areas and unit costs and shows the source of every figure.

Page 1 of the ROM estimate: $/SF range, cost by major system and additions for soft costs and contingency, totaling $6,396,000

What goes in.

You

Need a rough order-of-magnitude construction cost for a 12,000 sf two-story medical office building in the Dallas area, 2026 dollars, Type V-B, sprinklered, mid-grade finishes, surface parking. Give me a $/sf range, a breakdown by major system, and what to carry for soft costs and contingency.

Test project: Standard blind-test question without project files: fictitious 12,000 sf two-story medical office building in the Dallas area; estimate issued as 'Trinity Street Architects (fictitious)'.

What ArchX gives back.

Page 1 of the ROM estimate: $/SF range, cost by major system and additions for soft costs and contingency, totaling $6,396,000
Page 1 of the ROM estimate: $/SF range, cost by major system and additions for soft costs and contingency, totaling $6,396,000

From the answer

Carry $350–$475 per gross SF for construction: $4.20–$5.70 million in 2026 Dallas-area dollars. This includes the completed building, medical office finishes, ordinary sitework, surface parking, and contractor overhead/profit.

Saved files

  • ROM Estimate Summary.pdf – 2-page ROM estimate: $/SF range, cost by major system, soft costs and contingency, assumptions and exclusions
  • Cost Review.xlsx – Editable cost workbook

Measured, not estimated.

4 min 11 s

ArchX working time for this brief, measured.

Run of October 30, 2026

$350–$475 per gross SF

construction cost range, 2026 Dallas-area dollars

Run of October 30, 2026

$410 per gross SF

working construction figure, $4.92 million for 12,000 SF

Run of October 30, 2026

$6.4 million

working project budget including soft costs and contingencies

Run of October 30, 2026

How to.

Put the drawings and your unit costs in the project folder and say which estimate you need. Try ArchX free for 7 days with a task from your own firm.