Plan review.
Conflicts found before the field.

ArchX overlays sheets, finds what conflicts or is missing and marks it with its source.

Structural framing plan S-101 marked up: checked dimensions ticked in green, discrepancies crossed in red and numbered 002 to 007

What goes in.

You

Our structural engineer sent over S-101 (folder 'Structural'). Can you review it against our first floor plan A-101 Rev 3 in 'Architectural'? We were expecting S-101 Rev 3. I need a marked-up PDF with numbered comments (our dimension vs theirs), a short comment list, and the review action you'd stamp it with: No Exceptions Taken, Make Corrections Noted, Revise and Resubmit, or Rejected.

Files

  • S-101_Rev2_Framing_Plan.pdf
  • A-101_Rev3_First_Floor_Plan.pdf

Test project: Synthetic test project from the 0.0.91 blind evaluation: a sample residence with a fictitious structural engineer (“Sample Structural Engineers, PLLC”) and an owner named “J. & K. Sample”.

What ArchX gives back.

Structural framing plan S-101 marked up: checked dimensions ticked in green, discrepancies crossed in red and numbered 002 to 007
Structural framing plan S-101 marked up: checked dimensions ticked in green, discrepancies crossed in red and numbered 002 to 007
Review panel on the sheet: eight comments with ours and theirs, and the proposed review action Revise and Resubmit
Review panel on the sheet: eight comments with ours and theirs, and the proposed review action Revise and Resubmit

From the answer

Proposed review action: Revise and Resubmit. The received sheet is S-101 Rev 2, and significant coordination discrepancies remain against A-101 Rev 3.

Saved files

  • S-101_Rev2_Framing_Plan_Reviewed.pdf – Marked-up S-101 with numbered comments (ours vs theirs), comment list with corrective actions and response columns, proposed review action (3 pages)

Measured, not estimated.

4 min 24 s

ArchX working time for this brief, measured.

Run of November 1, 2026

8

numbered comments on the framing plan, each with our dimension and theirs

Run of November 1, 2026

1'-0"

north dimension chain re-added: it runs 1'-0" over the overall

Run of November 1, 2026

6" vs 4 1/2"

stud-wall thickness SW1: ours against theirs, which explains the deeper study

Run of November 1, 2026

How to.

Put the sheets in the project folder and say what should be checked against what. Try ArchX free for 7 days with a task from your own firm.