Excavation calculator.
Cubic yards and truckloads.
Bank volume of a rectangular pit with sloped or vertical sides, from the length, width and depth at the bottom. A pit 60 ft × 40 ft at the bottom and 10 ft deep with 1:1 side slopes holds 1,308.64 cu yd in the bank, 1,635.80 cu yd loose with a swell factor of 1.25, or 117 loads in 14 cu yd trucks.
Excavation calculator, architekten.frontierx.ch/en-us/tools/excavation-calculator/
Bank volume
1,308.64 cu yd
1,635.80 cu yd loose, 117 loads
Side slope: 1:1. Top of the pit: 80 ft × 60 ft.
| Step | Result |
|---|---|
| Area at the bottom, 60 ft × 40 ft | 2,400 sq ft |
| Area at half depth, 70 ft × 50 ft | 3,500 sq ft |
| Area at the top, 80 ft × 60 ft | 4,800 sq ft |
| Volume in cubic feet | 35,333.33 cu ft |
| Bank volume | 1,308.64 cu yd |
| Loose volume, swell factor 1.25 | 1,635.80 cu yd |
| Truckloads of 14 cu yd | 117 |
Working
- Top: 60 + 2 × 1 × 10 = 80 ft long, 40 + 2 × 1 × 10 = 60 ft wide.
- Half depth: 60 + 1 × 10 = 70 ft long, 40 + 1 × 10 = 50 ft wide.
- Prismoidal formula: depth ÷ 6 × (bottom + 4 × half depth + top) = 10 ÷ 6 × (2,400 + 4 × 3,500 + 4,800) = 35,333.33 cu ft.
- 35,333.33 cu ft ÷ 27 = 1,308.64 cu yd bank.
- Loose volume: 1,308.64 × 1.25 = 1,635.80 cu yd.
- Truckloads: 1,635.80 ÷ 14 = 116.84, rounded up to 117.
Rectangular bottom, level ground and the same slope on all four sides. 27 cubic feet make one cubic yard. The swell factor and the truck capacity are the ones you enter. The calculator does not check whether a slope is safe.
Your entries stay in this browser.
From two surveys, before and after the dig, ArchX computes the cubic yards inside the pay line and writes the report for the owner’s rep. Try free for 7 days
How the volume is worked out.
For a rectangular pit on level ground with the same slope on all four sides. The slope is the horizontal distance per 1 ft of depth.
- Top of the pit. Each sloped side moves out by slope × depth. Top length = bottom length + 2 × slope × depth, and the same for the width. With vertical walls the top equals the bottom.
- Three areas. The bottom, the top and the area at half the depth, where each side is the bottom side + slope × depth.
- Prismoidal formula. Volume in cubic feet = depth ÷ 6 × (bottom area + 4 × area at half depth + top area). For this shape the formula is exact.
- Cubic yards. Cubic feet ÷ 27. This is the bank volume, the soil as it sits in the ground.
- Loose volume. Bank cubic yards × the swell factor for your soil.
- Truckloads. Loose cubic yards ÷ what one truck carries, rounded up to whole loads.
Example: 60 ft × 40 ft at the bottom, 10 ft deep, side slopes 1:1. The top is 80 ft × 60 ft, half depth 70 ft × 50 ft. The areas are 2,400 sq ft, 3,500 sq ft and 4,800 sq ft. Volume = 10 ÷ 6 × (2,400 + 4 × 3,500 + 4,800) = 35,333.33 cu ft, and 35,333.33 ÷ 27 = 1,308.64 cu yd bank. With a swell factor of 1.25 that is 1,635.80 cu yd loose, and in 14 cu yd trucks 1,635.80 ÷ 14 = 116.84, so 117 loads.
The swell factor and the truck size in the example are entries, not recommendations. Take both from your soil report and your hauler.
What firms ask about excavation volume.
How do I calculate excavation in cubic yards?
Multiply length, width and depth in feet and divide by 27, the number of cubic feet in a cubic yard. That is exact for vertical walls: 60 ft × 40 ft × 10 ft is 24,000 cu ft, or 888.89 cu yd. With sloped sides the pit is wider at the top, so use the prismoidal formula: depth ÷ 6 × (bottom area + 4 × area at half depth + top area), then divide by 27. With 1:1 side slopes the same pit holds 1,308.64 cu yd.
Why not just average the top and bottom areas?
Because with sloped sides the area does not change in a straight line with depth, and averaging the two ends overstates the volume by two thirds × slope² × depth³. In the example, (2,400 + 4,800) ÷ 2 × 10 gives 1,333.33 cu yd: 24.69 cu yd more than the prismoidal 1,308.64 cu yd. With vertical walls both methods give the same figure.
What is the difference between bank and loose cubic yards?
Bank cubic yards are the soil as it sits in the ground. Once dug it takes more room, so hauling and disposal are counted in loose cubic yards: bank volume times the swell factor. Soil placed and compacted as fill is a third measure, which this calculator does not compute.
What swell factor should I enter?
The one for your soil, from the geotechnical report or your earthwork contractor. The factor is loose volume divided by bank volume, so 1.25 means the soil takes 25% more room once dug; you can enter 1.25 or 25%. The calculator has no built-in values, because the factor depends on the soil on your site.
What side slope should I enter?
The slope the pit will actually be dug to, from the geotechnical report, the protective system design or the contractor’s excavation plan. Where workers are protected by sloping under OSHA’s Appendix B to 29 CFR 1926 Subpart P, the maximum allowable slopes for excavations less than 20 feet deep are vertical in stable rock, 3/4:1 in Type A soil, 1:1 in Type B and 1½:1 in Type C, horizontal to vertical. Sloping for excavations deeper than 20 feet must be designed by a registered professional engineer. The calculator does not check whether a slope is safe.
How many truckloads will the dig take?
Loose cubic yards divided by what one truck carries per load, rounded up, because a part load is still a trip. In the example, 1,635.80 ÷ 14 = 116.84, so 117 loads. Use the load your hauler actually carries.
Does it work for a sloping site or an irregular pit?
No. It assumes level ground, a rectangular bottom and the same slope on all four sides. For anything else the volume comes from two surfaces: the ground before and after the dig, or the existing survey and the design. That is how ArchX works out excavation from two drone scans. Excavation cubic yards from two drone scans
Where the figures come from.
The maximum slopes of OSHA’s Appendix B and the size of a cubic yard, from the official texts. The formula itself needs no source: it is the geometry of the pit.
A rectangle is easy.
Real ground takes two surveys.
From two drone scans, before and after the dig, ArchX computes the cubic yards inside the pay line, filters the excavator out of the scan and writes a report for the owner’s rep with sections, a workbook, a 3D view and a script that recomputes the figure. Try it free for 7 days on Mac or Windows, without payment details.