Pay application calculator.
Check the payment due before you certify.

The summary of a pay application, line by line: contract sum to date, retainage on completed work and on stored materials, previous certificates, the current payment due and the balance to finish. With $551,112.75 completed and stored, 10% and 5% retainage and $402,615.00 previously certified, $95,324.74 is due.

Pay application calculator, architekten.frontierx.ch/en-us/tools/pay-application-calculator/

Contract

From the agreement (line 1).

Executed change orders only, with a minus sign when deductions outweigh additions (line 2).

Work to date

From previous applications plus this period: columns D and E of the continuation sheet.

Not yet in the work: column F. Enter 0 if there are none.

Retainage

Your agreement sets the rate and what it applies to (lines 5a and 5b). Enter 0 where it holds no retainage.

Payments

Line 6 of the last certificate for payment: the amount certified, not the amount paid. Enter 0 on the first application.

The current payment due on their application (line 8), to see the difference.

Current payment due (line 8)

$95,324.74

The contractor requested $98,500.00: $3,175.26 more than these figures give.

Completed and stored: 43.4% of the contract sum to date. Still to do: $717,337.25.

LineAmount
Original contract sum (line 1)$1,250,000.00
Net change by change orders (line 2)$18,450.00
Contract sum to date (line 3)$1,268,450.00
Completed and stored to date (line 4)$551,112.75
Retainage on completed work, 10% (line 5a)$51,234.75
Retainage on stored materials, 5% (line 5b)$1,938.26
Total retainage (line 5)$53,173.01
Earned less retainage (line 6)$497,939.74
Less previous certificates (line 7)$402,615.00
Current payment due (line 8)$95,324.74
Balance to finish, retainage included (line 9)$770,510.26
Requested by the contractor$98,500.00
Requested less computed$3,175.26
Working
  1. Line 3 = line 1 ± line 2 = $1,250,000.00 + $18,450.00 = $1,268,450.00.
  2. Line 4 = work completed + materials stored = $512,347.50 + $38,765.25 = $551,112.75.
  3. Line 5a = 10% × $512,347.50 = $51,234.75.
  4. Line 5b = 5% × $38,765.25 = $1,938.2625, rounded to $1,938.26.
  5. Line 5 = 5a + 5b = $51,234.75 + $1,938.26 = $53,173.01.
  6. Line 6 = line 4 − line 5 = $551,112.75 − $53,173.01 = $497,939.74.
  7. Line 8 = line 6 − line 7 = $497,939.74 − $402,615.00 = $95,324.74.
  8. Line 9 = line 3 − line 6 = $1,268,450.00 − $497,939.74 = $770,510.26: $717,337.25 of work still to do plus $53,173.01 retainage held.
  9. Requested less computed = $98,500.00 − $95,324.74 = $3,175.26.

Line numbers as on the summary of the AIA’s G702. This calculator is not an AIA document and does not replace the application, the continuation sheet or your certificate. Your agreement sets the rate and basis of retainage. Each retainage line is rounded to the cent.

Your entries stay in this browser.

ArchX reviews the whole application against your agreement, the certificate log and the field report, and drafts the worksheet and the letter for your signature. Try free for 7 days

How the payment due is worked out.

Line numbers as on the summary of the AIA’s G702, the application and certificate for payment. The labels are our own.

  1. Original contract sum, line 1. From the agreement.
  2. Net change by change orders, line 2. Executed change orders only. Deductive change orders reduce it.
  3. Contract sum to date, line 3. Line 1 plus or minus line 2.
  4. Completed and stored to date, line 4. Work completed from previous applications and this period, plus materials presently stored and not yet in the work. On the continuation sheet these are columns D, E and F, totaled in column G.
  5. Retainage, line 5. A percentage of completed work (5a, columns D and E) plus a percentage of stored material (5b, column F), at the rates and on the basis your agreement sets. Where line items carry different rates, column I of the continuation sheet holds the retainage line by line.
  6. Earned less retainage, line 6. Line 4 less line 5.
  7. Less previous certificates, line 7. Line 6 of the last certificate for payment, as certified, not as paid.
  8. Current payment due, line 8. Line 6 less line 7.
  9. Balance to finish, retainage included, line 9. Line 3 less line 6: the work still to do plus the retainage held.

Example: an original contract sum of $1,250,000.00 and $18,450.00 in executed change orders give $1,268,450.00. Work completed to date is $512,347.50 and materials stored $38,765.25, together $551,112.75. Retainage is 10% of $512,347.50 = $51,234.75 and 5% of $38,765.25 = $1,938.26, rounded to the cent, together $53,173.01. Earned less retainage: $497,939.74. Less $402,615.00 previously certified, $95,324.74 is due, and $770,510.26 remains to finish, retainage included.

This page is not an AIA document. AIA, G702 and G703 belong to The American Institute of Architects; the calculator is not affiliated with the AIA and does not reproduce its forms. Your agreement decides the rate and basis of retainage, and you decide what to certify.

What architects ask before they certify.

How is the current payment due calculated?

Work completed and materials stored to date, less the total retainage, is the amount earned less retainage (line 6). Less the previous certificates for payment (line 7), that is the current payment due (line 8). In the example: $551,112.75 less $53,173.01 retainage is $497,939.74, and less $402,615.00 previously certified, $95,324.74 is due.

Is retainage held on stored materials?

Only as your agreement says. The summary has two retainage lines, a percentage of completed work (5a) and a percentage of stored material (5b), so the two rates can differ. The AIA notes that retainage requirements come from the contract documents and may also be affected by applicable law. Enter 0 where the agreement holds none. In the example, 10% of $512,347.50 and 5% of $38,765.25 make $53,173.01.

What goes in as previous certificates?

Line 6 of the last certificate for payment: the total earned less retainage that was certified. Take the amounts certified, not the cash paid; a disputed amount from an earlier certificate stays with that certificate rather than being deducted again. On the first application, enter 0.

Which change orders count?

Executed change orders only. Pending change requests stay outside the contract sum until they are executed. A deductive change order reduces the net change; if deductions outweigh additions, enter the net with a minus sign.

What if I certify less than the contractor requested?

Then your certificate shows a different amount. The G702 asks the architect to attach an explanation when the amount certified differs from the amount applied for, and to initial the figures changed on the application and the continuation sheet. Give your reasons in writing to the owner and the contractor within the time your agreement sets. Enter the contractor’s figure in the last field to see the difference: in the example they asked for $98,500.00, $3,175.26 more than the figures give. How architects review a pay application

Why does the balance to finish include retainage?

Because the retainage has not been paid yet. Line 9 is line 3 less line 6. In the example, $717,337.25 of work still to do plus $53,173.01 retainage held make $770,510.26.

Is this an AIA document?

No. AIA, G702 and G703 belong to The American Institute of Architects. This calculator is not an AIA document and not affiliated with the AIA. It follows the line logic of the G702 summary in its own words and does not reproduce, fill in or replace the form. It runs in your browser and sends your figures nowhere.

The summary adds up.
ArchX checks the rest.

ArchX reviews the whole application against the agreement, your certificate log and the field report: every line of the schedule of values, stored materials, change orders and retainage. It writes a worksheet you can check, a workbook with formulas and a draft letter with each adjustment and its basis. It does not certify: you check the result and sign, and the letter stays a draft until you send it. Try it free for 7 days on Mac or Windows, without payment details.