Excavation calculator.
Cubic metres and lorry loads.
In-situ volume of a rectangular dig with battered or vertical sides, from the length, width and depth at the base. A dig 18 m × 12 m at the base and 3 m deep with 1:1 batters is 954 m³ in situ, 1,192.50 m³ bulked with a bulking factor of 1.25, or 120 loads in 10 m³ lorries.
Excavation calculator, architekten.frontierx.ch/en-gb/tools/excavation-calculator/
In-situ volume
954 m³
1,192.50 m³ bulked, 120 loads
Batter: 1:1. Top of the dig: 24 m × 18 m.
| Step | Result |
|---|---|
| Area at the base, 18 m × 12 m | 216 m² |
| Area at half depth, 21 m × 15 m | 315 m² |
| Area at the top, 24 m × 18 m | 432 m² |
| In-situ volume | 954 m³ |
| Bulked volume, bulking factor 1.25 | 1,192.50 m³ |
| Lorry loads of 10 m³ | 120 |
Working
- Top: 18 + 2 × 1 × 3 = 24 m long, 12 + 2 × 1 × 3 = 18 m wide.
- Half depth: 18 + 1 × 3 = 21 m long, 12 + 1 × 3 = 15 m wide.
- Prismoidal formula: depth ÷ 6 × (base + 4 × half depth + top) = 3 ÷ 6 × (216 + 4 × 315 + 432) = 954 m³.
- Bulked volume: 954 × 1.25 = 1,192.50 m³.
- Lorry loads: 1,192.50 ÷ 10 = 119.25, rounded up to 120.
Rectangular base, level ground and the same batter on all four sides. The bulking factor and the lorry capacity are the ones you enter. The calculator does not check whether a batter is safe.
Your entries stay in this browser.
From two surveys, before and after the dig, ArchX computes the cubic metres inside the measurement boundary and writes the report for the QS. Try free for 7 days
How the volume is worked out.
For a rectangular dig on level ground with the same batter on all four sides. The batter is the horizontal distance per 1 m of depth.
- Top of the dig. Each battered side moves out by batter × depth. Top length = base length + 2 × batter × depth, and the same for the width. With vertical sides the top equals the base.
- Three areas. The base, the top and the area at half the depth, where each side is the base side + batter × depth.
- Prismoidal formula. In-situ volume = depth ÷ 6 × (base area + 4 × area at half depth + top area). For this shape the formula is exact.
- Bulked volume. In-situ volume × the bulking factor for your ground.
- Lorry loads. Bulked volume ÷ what one lorry carries, rounded up to whole loads.
Example: 18 m × 12 m at the base, 3 m deep, batters 1:1. The top is 24 m × 18 m, half depth 21 m × 15 m. The areas are 216 m², 315 m² and 432 m². Volume = 3 ÷ 6 × (216 + 4 × 315 + 432) = 954 m³ in situ. With a bulking factor of 1.25 that is 1,192.50 m³ bulked, and in 10 m³ lorries 1,192.50 ÷ 10 = 119.25, so 120 loads.
The bulking factor and the lorry size in the example are entries, not recommendations. Take both from your ground investigation and your haulier.
What practices ask about excavation volume.
How do I calculate excavation volume in cubic metres?
Multiply length, width and depth in metres. That is exact for vertical sides: 18 m × 12 m × 3 m is 648 m³. With battered sides the dig is wider at the top, so use the prismoidal formula: depth ÷ 6 × (base area + 4 × area at half depth + top area). With 1:1 batters the same dig is 954 m³.
Why not just average the top and bottom areas?
Because with battered sides the area does not change in a straight line with depth, and averaging the two ends overstates the volume by two thirds × batter² × depth³. In the example, (216 + 432) ÷ 2 × 3 gives 972 m³: 18 m³ more than the prismoidal 954 m³. With vertical sides both methods give the same figure.
What is the difference between in-situ and bulked volume?
In-situ volume is the material as it sits in the ground, before digging. Once dug it takes more room, so muck away and disposal are counted in bulked volume: in-situ volume times the bulking factor. Material placed and compacted as fill is a third measure, which this calculator does not work out.
What bulking factor should I enter?
The one for your ground, from the ground investigation report or your groundworks contractor. The factor is bulked volume divided by in-situ volume, so 1.25 means the material takes 25% more room once dug; you can enter 1.25 or 25%. The calculator has no built-in values, because the factor depends on the ground on your site.
What batter should I enter?
The one the dig will actually have, from the temporary works design, the ground investigation or the contractor’s method statement. HSE’s guidance on excavations says that battering the sides to a safe angle of repose may make an excavation safer, that in granular soils the slope should be less than the natural angle of repose of the material, and that wet ground needs a considerably flatter slope. HSE gives no single figure, and the calculator does not check whether a batter is safe.
How many lorry loads will the dig take?
Bulked volume divided by what one lorry carries per load, rounded up, because a part load is still a trip. In the example, 1,192.50 ÷ 10 = 119.25, so 120 loads. Use the load your haulier actually carries.
Does it work for a sloping site or an irregular dig?
No. It assumes level ground, a rectangular base and the same batter on all four sides. For anything else the volume comes from two surfaces: the ground before and after the dig, or the existing survey and the design. That is how ArchX works out excavation from two drone surveys. Excavation from two surveys, with the QS report
Where the guidance comes from.
The formula itself needs no source: it is the geometry of the dig. On batters, the Health and Safety Executive’s guidance on excavations.
A rectangle is easy.
Real ground takes two surveys.
From two drone surveys, before and after the dig, ArchX works out the cubic metres inside the measurement boundary, filters the excavator out of the survey and writes a report for the QS with plan, difference map, sections, a workbook, a 3D view and a recalculation package. Try it free for 7 days on Mac or Windows, without payment details.