Excavation.
Cubic metres from two surveys.

ArchX works out the dig from point clouds or drawings: volume, wagon loads and the measurement boundary, shown in 3D.

Page 1 of the QS report: 2,754 m³ cut, status, what the quantity rests on, items to confirm before payment and sensitivity scenarios

What goes in.

You

We've got two drone surveys of the basement dig at the Mews House: existing_2026-03-02.las from before we started and excavated_2026-09-15.las from last month (the excavator was still in the hole). How many cubic metres have actually come out? The contractor is claiming for more, so I need a report I can send to the QS. The sheet piling line is roughly …

Files

  • existing_2026-03-02.las
  • excavated_2026-09-15.las

Test project: Blind-test task 0.0.91: two synthetic drone point clouds (LAS header 'ArchX synthetic fixture') of a fictitious 'Mews House' basement dig; report issued under the test practice profile.

What ArchX gives back.

Page 1 of the QS report: 2,754 m³ cut, status, what the quantity rests on, items to confirm before payment and sensitivity scenarios
Page 1 of the QS report: 2,754 m³ cut, status, what the quantity rests on, items to confirm before payment and sensitivity scenarios
Difference map of the dig: cut depth inside the quantity boundary, gaps and section lines
Difference map of the dig: cut depth inside the quantity boundary, gaps and section lines

From the answer

The supplied files model approximately 2,754 m³ of in-situ excavation within your 600 m² piling rectangle, between 2 March and 15 September 2026.

Saved files

  • Excavation_2026-11-01_Mews_P1.pdf – QS report, 11 pages: quantity, plan, difference map, sections, step-by-step proof, gaps and sensitivity scenarios
  • Excavation_2026-11-01_Mews_P1.xlsx – Calculation workbook with live formulas
  • Excavation_2026-11-01_Mews_P1_Audit_package.zip – Reproducible calculation package: source files, point, triangle and grid files and a recompute script
  • Excavation_2026-11-01_Mews_P1_3D.html – Interactive 3D view of the dig
  • Excavation_2026-11-01_Mews_P1_Geometry.dxf – Quantity boundary and geometry for CAD

Measured, not estimated.

4 min 57 s

ArchX working time for this brief, measured.

Run of 1 November 2026

2,754 m³

in-situ excavation between the two drone surveys, excavator filtered out

Run of 1 November 2026

182.1 m³

of that on areas with weaker point support, reported separately

Run of 1 November 2026

28.3 m³

effect of moving the boundary inwards (sensitivity test)

Run of 1 November 2026

How to.

Put the surveys before and after the dig in the project folder and ask for the volume. Try ArchX free for 7 days with a task from your own practice.