Contract administration.
Applications checked.
ArchX checks the contractor’s interim application against the contract and your valuation and prepares the certificate ready to sign.

What goes in.
You
Pennine Oak's Application for Payment No. 5 for the two houses at Ashgrove Lane has come in (Contractor/Application for Payment No 5.pdf). Please check it against the contract, our site valuation record and the certificate register, and prepare Interim Certificate No. 5 for me to sign, with a covering letter to Pennine Oak explaining where our figure differs from theirs.
Files
- Application for Payment No 5.
pdf - Contract Particulars and Contract Sum Analysis.
pdf - Priced Schedule of Rates -
External Works. pdf - Site valuation record 26-
10- 2026. xlsx - Certificate register.
xlsx - CAI-
03 Triple- glazed rooflights. pdf - CAI-
05 Plot 2 rear terrace. pdf - Variation Quotation VQ-
04. pdf - Contractor's Programme Rev B.
pdf
Test project: England, with planted errors. A fictitious practice, “Northgate Architects (fictitious)”, a fictitious employer and contractor, two new houses under JCT Minor Works 2024. One run with ChatGPT Pro (GPT 6.1 Sol, very high) and the same code as ArchX 0.1.3, sent to every practice on 6 November 2026.
What ArchX gives back.



From the answer
Prepared Interim Certificate No. 5 for £113,861.61 excluding VAT, with payment by 16 November 2026.
The letter explains three adjustments to the application, page 1:
- £5,525 additional foundation work excluded pending instruction and pricing evidence.
- Retention corrected from 1.5% to 3%.
- Certificate No. 3 corrected from £74,346 to £79,346.
VAT is shown at 0%, assuming both houses qualify under HMRC Notice 708. Confirm that basis and any Construction Industry Scheme deduction with Harrowfield’s accountant; the pay less notice deadline is 11 November.
Nothing has been sent; once sent, record the issue. The certificate is not a pay less notice.
Saved files
- IC-
05 Interim certificate. – Interim Certificate No. 5 with Annex A: valuation line by line, earlier certificates, due date, pay less date and final date for payment; left for your name, signature and datepdf and . docx - LET-
01 Interim Certificate No. – Covering letter to the contractor: their figure against yours, with the reason for each adjustment; not sent5 – valuation and reconciliation. pdf and . docx - IC-
05 Interim certificate – valuation and reconciliation. – Workbook to recalculate: the reconciliation checks return zeroxlsx - Document register.
xlsx – The practice's document register, with the certificate and the letter entered
Measured, not estimated.
ArchX working time for this brief, measured.
Run of 6 November 2026
less than the contractor applied for, excluding VAT: £130,142.87 applied for, £113,861.61 certified. The application also charged VAT at 20%; ArchX shows 0% for new dwellings and asks you to confirm it
Run of 6 November 2026
planted errors found: a claim without an instruction, retention at 1.5% instead of 3%, an earlier certificate entered £5,000 too low, and VAT at 20% on zero-rated new houses
Run of 6 November 2026
the certificate matches our control calculation: £113,861.61
Run of 6 November 2026
How to.
Put the application, the contract particulars and your valuation in the project folder and ask for the check. Try ArchX free for 7 days with a task from your own practice.