Plot ratio calculator.
Floor area and site coverage, free.
Plot ratio is the total floor area of a building divided by the site area. On a 1,200 m² site, a plot ratio of 2.0 permits 2,400 m² of floor area, and 50% site coverage permits a 600 m² footprint. A scheme of 2,080 m² on a 520 m² footprint has a plot ratio of 1.733 and leaves 320 m².
Plot ratio calculator, architekten.frontierx.ch/en-gb/tools/plot-ratio-calculator/
Still possible, floor area
320 m²
Site area: 1,200 m² (0.12 ha)
| Figure | Project | Permitted | Area permitted | Still possible |
|---|---|---|---|---|
| Plot ratio (floor area) | 1.733 | 2.0 | 2,400 m² | 320 m² |
| Site coverage (footprint) | 43.33% | 50% | 600 m² | 80 m² |
Working
- Plot ratio of the project = 2,080 m² ÷ 1,200 m² = 1.733; permitted floor area = 2.0 × 1,200 m² = 2,400 m²; still possible = 2,400 m² − 2,080 m² = 320 m² (86.67% of the permitted floor area used).
- Site coverage of the project = 520 m² ÷ 1,200 m² × 100 = 43.33%; permitted building footprint = 50% × 1,200 m² = 600 m²; still possible = 600 m² − 520 m² = 80 m² (86.67% of the permitted building footprint used).
- Permitted floor area ÷ permitted footprint = 2,400 m² ÷ 600 m² = 4: the number of floors that use the whole plot ratio if every floor covers the whole permitted footprint.
Your local plan or code defines what counts as floor area, as footprint and as site area. The calculator takes the areas as you enter them.
Your inputs stay in this browser.
ArchX measures GIA and NIA from your drawings to the RICS Code of Measuring Practice and checks a planning application against the council’s validation requirements before you submit it. Try free for 7 days
How plot ratio and site coverage are worked out.
Each figure is one division by the site area, and the permitted area is the same division the other way round.
- Plot ratio of the scheme. Floor area ÷ site area.
- Permitted floor area. Permitted plot ratio × site area.
- Site coverage of the scheme. Building footprint ÷ site area × 100.
- Permitted footprint. Maximum site coverage × site area.
- Still possible. Permitted area − the scheme’s area. Below 0, the scheme is over the limit.
Example: a 1,200 m² site, a permitted plot ratio of 2.0 and a maximum site coverage of 50%. The scheme has 2,080 m² of floor area on a 520 m² footprint. Plot ratio = 2,080 m² ÷ 1,200 m² = 1.733. Permitted floor area = 2.0 × 1,200 m² = 2,400 m², so 320 m² are still possible. Site coverage = 520 m² ÷ 1,200 m² × 100 = 43.33%. Permitted footprint = 50% × 1,200 m² = 600 m², so 80 m² are left. Built over the whole permitted footprint, the permitted floor area takes 2,400 m² ÷ 600 m² = 4 storeys.
The limits in the example are entries, not the limits of a real site. Take yours from the plan or code that applies.
Which floor area counts depends on the plan.
Plot ratio is always the same division. What goes into it is not.
For major planning applications, the London Plan asks for the Floor Area Ratio as the total gross external area of all floors divided by the site area, and for the Site Coverage Ratio as the gross external area of ground floors divided by the site area (paragraph 3.3.23). London Plan Guidance on optimising site capacity encourages parameters on plot ratio and plot coverage: plot ratio is the ratio between site area and the total building floor area, plot coverage the proportion of the site area occupied by buildings.
In Ireland, the national guidelines on sustainable and compact settlements calculate plot ratio from the gross floor area, the sum of floorspace within the external walls. Auckland’s Unitary Plan keeps a separate definition of gross floor area for calculating floor area ratio.
So the calculator does not decide what to count. It takes the floor area, the footprint and the site area as you enter them. Measure them the way your plan does, and name the basis on the schedule.
The same figure under other names.
Terms and calculations as the official planning sources write them, read on 16 November 2026. What a council permits on a site is set in its own plan.
| Market | Term | Calculation | Source |
|---|---|---|---|
| London, England | Floor Area Ratio and Site Coverage Ratio | Total gross external area of all floors ÷ site area; gross external area of ground floors ÷ site area | The London Plan 2021, paragraph 3.3.23 |
| London, England | Plot ratio and plot coverage | The ratio between site area and the total building floor area; the proportion of the site area occupied by buildings | London Plan Guidance, Optimising Site Capacity (June 2023), section 4.5 |
| Ireland | Plot ratio and site coverage | Gross floor area, the sum of floorspace within the external walls, ÷ site area; site coverage is the percentage of the site covered by building structures, excluding public roads and footpaths | Sustainable and Compact Settlements Guidelines for Planning Authorities, Appendix A: Glossary of Terms |
| New South Wales, Australia | Floor space ratio (FSR), written as 3:1 | Maximum gross floor area = site area × FSR | NSW Department of Planning, LEP practice note PN 08-001, Height and floor space ratio |
| Auckland, New Zealand | Floor area ratio (FAR) and building coverage | Gross floor area ÷ site area, with a gross floor area defined for this purpose; building coverage is the part of the net site area covered by buildings | Auckland Unitary Plan, Chapter J1 Definitions |
| Toronto, Canada | Floor space index | Gross floor area, less the areas the by-law lists, ÷ the area of the lot | City of Toronto Zoning By-law 569-2013, regulation 40.5.40.40 (Commercial Residential zones) |
What practices ask about plot ratio.
How do you calculate plot ratio?
Divide the total floor area by the site area. London Plan Guidance describes plot ratio as the ratio between site area and the total building floor area. A scheme of 2,080 m² on a 1,200 m² site has a plot ratio of 1.733. The other way round, the permitted floor area is the plot ratio times the site area: 2.0 × 1,200 m² = 2,400 m².
Is plot ratio the same as floor area ratio, floor space ratio or floor space index?
It is the same division under different names. The London Plan says Floor Area Ratio, the Irish guidelines say plot ratio, New South Wales says floor space ratio, Auckland says floor area ratio and Toronto says floor space index. What counts as floor area and as site area differs from plan to plan.
Which floor area goes into the plot ratio?
The one your plan names. The London Plan asks major applications for the gross external area of all floors. The Irish guidelines take the floorspace within the external walls. Auckland defines its own gross floor area for calculating floor area ratio. The calculator takes the areas as you enter them. How to measure GIA and NIA
What is site coverage?
The share of the site covered by buildings. The London Plan’s Site Coverage Ratio is the gross external area of ground floors divided by the site area; London Plan Guidance calls the same idea plot coverage. Enter the footprint and the maximum percentage, and the calculator shows the permitted footprint and what is left.
Can I enter the ratio as 3:1?
Yes. The New South Wales practice note writes floor space ratio as 3:1, and the calculator reads 3:1, 3 and 3.0 the same way. In the practice note’s first example, 3:1 on 1,000 m² of site area gives a maximum gross floor area of 3,000 m².
How many square metres are in a hectare?
10,000. The SI Brochure of the BIPM gives 1 ha = 1 hm² = 10⁴ m². A site of 0.12 ha is 1,200 m². Choose hectares next to the site area, or type ‘ha’ after the number.
Are my numbers stored?
No. The calculator runs in your browser and sends your inputs to no server. ‘Copy link’ puts your inputs into the link, and you decide who gets it.
Where the terms come from.
Definitions and examples from the official texts, read on 16 November 2026. The formula itself is one division.
- Greater London Authority: The London Plan 2021, paragraph 3.3.23 (Floor Area Ratio, Site Coverage Ratio)
- Greater London Authority: London Plan Guidance, Optimising Site Capacity: A Design-led Approach (June 2023), section 4.5
- gov.ie: Sustainable and Compact Settlements Guidelines for Planning Authorities, Appendices, Appendix A: Glossary of Terms
- NSW Department of Planning: LEP practice note PN 08-001, Height and floor space ratio
- Auckland Council: Auckland Unitary Plan, Chapter J1 Definitions
- City of Toronto: Zoning By-law 569-2013 (office consolidation), Chapter 40.5
- BIPM: The International System of Units (SI Brochure, 9th edition), Table 8 (1 ha = 10⁴ m²)
The ratio is done.
ArchX measures the drawings.
ArchX measures GIA and NIA from your drawings to the RICS Code of Measuring Practice and checks a planning application against the council’s validation requirements before you submit it. You check the result. Try it free for 7 days on Mac or Windows, without payment details. After that, £169 a month for your practice, including the first person; each additional person £42 a month. Prices exclude VAT.