Pay less notices.
Work out the last day.

Work out the due date, final date for payment and last day for a pay less notice under JCT, with worked dates, the Scheme default and a test certificate.

What is the last day for a pay less notice under JCT?

Count back from the final date for payment. JCT’s own explanation for its Standard Building Contract with Quantities gives 5 days before the final date, with the final date 14 days after the due date and the due date 7 days after the interim valuation date. Where a contract sets no period, the Scheme for Construction Contracts in England and Wales gives 7 days before a final date 17 days after the due date. The dates in your own contract particulars decide; read them first.

The date series, worked through

From the England test project in this guide, under JCT Minor Works 2024 as its contract particulars set it out:

  • Interim valuation date: Monday 26 October 2026.
  • Due date, 7 days later: Monday 2 November 2026.
  • Latest certificate date in the test particulars: 7 November 2026, a Saturday, so in practice issue by Friday 6 November.
  • Latest pay less notice, 5 days before the final date: Wednesday 11 November 2026.
  • Final date for payment, 14 days after the due date: Monday 16 November 2026.

Contract period or Scheme default

JCT periods apply when the contract says so. The Scheme applies where the parties have not agreed the period: paragraph 8(2) sets the final date at 17 days from the date payment becomes due, and paragraph 10 requires a pay less notice no later than 7 days before it. Scotland has its own Scheme. A certificate does not replace the notice: to pay less than the sum certified or notified, the payer gives a pay less notice stating the sum considered due and how it is calculated.

Count the days as your contract does

How days are counted can move the date. The contract particulars in the test project count calendar days, excluding public holidays in England, so around Christmas or Easter the dates can move. Check the wording in your own particulars before you rely on a date.

How to do it.

  1. 01

    Read the particulars

    The interim valuation dates and any stated periods.

  2. 02

    Set the due date

    From the interim valuation date.

  3. 03

    Set the final date

    From the due date.

  4. 04

    Count back

    The last day for a pay less notice from the final date.

  5. 05

    Put it on the certificate

    State the dates on the file, so the client sees the deadline before it passes.

A test project: the dates on Interim Certificate No. 5.

On an England test project, ArchX worked out the payment dates from the contract particulars and put them on Annex A of the certificate, with what a pay less notice has to state. In its answer it adds that the certificate is not a pay less notice.

Annex A of the certificate: the valuation line by line, the claim left out with its reason, the earlier certificates and the payment dates
Annex A of the certificate: the valuation line by line, the claim left out with its reason, the earlier certificates and the payment dates
6 min 14 s

ArchX working time, measured

£16,281.26

less than the contractor applied for, excluding VAT: £130,142.87 applied for, £113,861.61 certified. The application also charged VAT at 20%; ArchX shows 0% for new dwellings and asks you to confirm it

4 of 4

planted errors found: a claim without an instruction, retention at 1.5% instead of 3%, an earlier certificate entered £5,000 too low, and VAT at 20% on zero-rated new houses

Test project: England, with planted errors. A fictitious practice, “Northgate Architects (fictitious)”, a fictitious employer and contractor, two new houses under JCT Minor Works 2024. One run with ChatGPT Pro (GPT 6.1 Sol, very high) and the same code as ArchX 0.1.3, sent to every practice on 6 November 2026. See the whole result

Asked briefly.

Does ArchX give legal advice on payment notices?

No. ArchX reads your contract particulars, works out the dates and puts them on the draft. You check them, and take legal advice where a dispute is likely.

What goes into a pay less notice?

The sum the payer considers due and the basis on which it is calculated. The annex in the example says so, and gives the latest date for the notice.

Is the date series the same under every JCT contract?

No. It depends on the contract and its particulars. The periods here come from JCT’s own explanation for SBC/Q and from the contract particulars of the test project under JCT Minor Works 2024.